Phase One

  • Reconstruction of Outdoor Arena
  • Completed

Phase Two

  • Indoor Arena
  • Two Phases at $300,000 for half the building and $500,000 for the entire building due to the increase price of material.

Phase Three

  • Classroom/Labs/Offices/Landscaping
  • $250,000 needed